Our client is a leading medtech company with 46k employees. Earlier this year, they faced the challenge of improving the efficiency of their Product Lifecycle Management (PLM) process. To stay competitive, they needed to identify bottlenecks within their manufacturing processes and identify areas for improvement. Failure to address these challenges would result in potential time and profit losses. After initial attempts to resolve the issues internally proved unsuccessful, the company approached SPK and Associates.
The Problem
The PLM process within the company:
-
- Suffered from inefficiencies in analyzing output.
- Lacked automated metrics to identify bottlenecks.
- Additionally, manual data organization and graph generation in Excel consumed significant time and resources.
Without a solution, critical issues such as prolonged bottlenecks and inefficiencies would persist. Ultimately, these would filter through to their bottom line and would negatively affect it.
The Solution
To address these challenges, the project sponsor, Steve, collaborated with SPK for our technology consulting expertise. Together, we developed a Python script that could extract and translate data from the client’s PLM tool and Creo into graphs. Now these could display essential metrics. Technologies such as VS Code, Python, Excel, the client’s PLM tool, and SWPDM were also utilized.
Earlier Error Identification
70 hours to deliver
7 hours per day saved
The approach to a successful delivery saw the project divided into three phases:
The first and second phases were almost simultaneous and took about 70 hours over the course of 6 weeks.
The Results
The implemented solution delivered significant benefits to our client. For example:
-
- The automated metrics provided actionable insights enabling the identification of negative trends in key areas, such as the time taken to release Design Release Work Orders (DRWs) and the rate of DRW rejections. By addressing these issues promptly, Steve and his team reduced DRW release time. This resulted in increased product sales and cost savings.
- Additionally, the automation of data analysis and graph generation saved considerable time. What used to take hours or even days of manual effort could now be completed in just minutes. The time savings were estimated to be approximately 7 hours per analysis, allowing the team to focus on more value-added tasks.
- Moreover, the graphical representation of data improved the quality of the PLM process. It became easier to identify process steps with execution errors or inefficiencies, such as mislabeling or omitting Engineering Change Order (ECO) numbers. Armed with this information, our client could now take targeted actions to address these issues and combat negative trends. For example, by restricting the comments field to only ECO numbers.
Looking ahead, the project laid the foundation for future automation phases. The completion of the research and manual
graph generation phases within approximately six weeks demonstrated the potential for further improvements and
scalability
We’re delighted with the solution. 7 hours saved per day from manual labor analysis is nearly one full FTE saved for the entire year. Additionally, it’s efficiencies that will filter to our bottom line and reduce errors. I would definitely work with SPK again.
Conclusion
Through their collaboration with SPK, our client successfully transformed their PLM process, addressing inefficiencies and
improving key metrics. The implementation of automated metrics resulted in significant time and cost savings, enhanced
efficiency, and improved product quality.
This case study showcases the power of technology-driven solutions in revolutionizing operational processes within the
medical technology industry, ultimately driving success and competitiveness for companies like this medtech company.
If you need support optimizing your PLM processes, contact our team here.
Get a no-obligation initial assessment
Whether you’re trying to solve technical problems, implement new technology tools and strategies, or improve efficiency, SPK and Associates can be a key part of your strategy. We can provide a free, no-obligation initial assessment on almost any technology or engineering situation. Contact us today at (888) 310-4540 or info@spkaa.com.